🔗 New or bigger grid connection in Sweden: how long may it take and who do I complain to?

The short answer

A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.

📜 The rules in Sweden

Grid connection

The grid company must connect you within a reasonable time. The Electricity Act sets two years from your request as the limit unless longer is necessary, but Ei stresses that a much shorter time is often reasonable. The connection fee must be reasonable.

  • Ei can review the connection fee, the time taken, extra costs and other terms free of charge. Your request must reach Ei within two years of the binding offer (or the invoice date). (ei.se)
Official source: konsumentforum.ei.se · Checked 2026-09-30

🪜 Step by step

  1. Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
  2. Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for Sweden below.
  3. Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
  4. Complain if it goes wrongComplain to the grid operator first, then to the body named below.

📇 Who to contact

Energimarknadsinspektionen (Ei)Supervises energy companies and explains your rightsFor information, and to report a company that breaks the rules📞 016-16 27 00🔗 ei.se
Allmänna reklamationsnämnden (ARN)Settles disputes with energy companiesWhen the company has not solved your complaint🔗 www.arn.se

❓ Questions

Who pays for the connection?

Usually the customer pays a connection charge set by the grid operator or the regulator.

Why does my grid operator refuse or delay?

Sometimes the local grid is full. Ask for the reason and the expected date in writing.

Do I need a new connection for solar panels?

Often not for small systems, but you usually have to register them with the grid operator.