🔗 New or bigger grid connection in Latvia: how long may it take and who do I complain to?

The short answer

A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.

📜 The rules in Latvia

Grid connection

For a new or changed connection, the grid operator (mostly Sadales tīkls) must give you technical requirements within 20 days of your application, and connect your installation within 10 days after you report it is ready. The cost is the zone's rate per load unit times your permitted load, plus connection costs.

  • These SPRK connection rules were adopted on 23 April 2026 and apply from 1 May 2026. (likumi.lv)
Official source: likumi.lv · Checked 2026-09-30

🪜 Step by step

  1. Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
  2. Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for Latvia below.
  3. Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
  4. Complain if it goes wrongComplain to the grid operator first, then to the body named below.

📇 Who to contact

AS "Sadales tīkls" — galvenais elektroenerģijas sadales sistēmas operators LatvijāRuns the local grid, meters and connectionsPower cut, meter problem, new connection📞 8404🔗 sadalestikls.lv/lv/kontakti
Sabiedrisko pakalpojumu regulēšanas komisija (SPRK)Supervises energy companies and explains your rightsFor information, and to report a company that breaks the rules📞 +371 67097200🔗 www.sprk.gov.lv
Sabiedrisko pakalpojumu regulēšanas komisija (SPRK) – sūdzības un strīdiSettles disputes with energy companiesWhen the company has not solved your complaint📞 +371 67097200🔗 www.sprk.gov.lv/lv/sudzibu-izskatisana-0

❓ Questions

Who pays for the connection?

Usually the customer pays a connection charge set by the grid operator or the regulator.

Why does my grid operator refuse or delay?

Sometimes the local grid is full. Ask for the reason and the expected date in writing.

Do I need a new connection for solar panels?

Often not for small systems, but you usually have to register them with the grid operator.

📎 Sources

Checked: 2026-09-30