🔗 New or bigger grid connection in Liechtenstein: how long may it take and who do I complain to?

The short answer

A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.

📜 The rules in Liechtenstein

Grid connection

LKW charges the property owner a connection fee (Netzanschlussbeitrag) and a grid cost contribution (Netzkostenbeitrag) based on the costs of an efficiently run grid. The Kommission für Energiemarktaufsicht approves both connection and grid-use prices.

  • For a new installation or a change to an existing connection, an installation notice must reach LKW early, before work begins. (lkw.li)
Official source: lkw.li · Checked 2026-09-30

🪜 Step by step

  1. Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
  2. Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for Liechtenstein below.
  3. Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
  4. Complain if it goes wrongComplain to the grid operator first, then to the body named below.

📇 Who to contact

Liechtensteinische Kraftwerke (LKW) — Whole countryRuns the local grid, meters and connectionsPower cut, meter problem, new connection📞 +423 236 01 11🔗 www.lkw.li
Kommission für EnergiemarktaufsichtSupervises energy companies and explains your rightsFor information, and to report a company that breaks the rules
Schlichtungsstelle nach Elektrizitätsmarkt- und Gasmarktgesetz (Kommission für Energiemarktaufsicht)Settles disputes with energy companiesWhen the company has not solved your complaint

❓ Questions

Who pays for the connection?

Usually the customer pays a connection charge set by the grid operator or the regulator.

Why does my grid operator refuse or delay?

Sometimes the local grid is full. Ask for the reason and the expected date in writing.

Do I need a new connection for solar panels?

Often not for small systems, but you usually have to register them with the grid operator.