New or bigger grid connection in France: how long may it take and who do I complain to?
A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.
FFCheck One: every FFCheck Letter included, €4.99 a month
A formal letter for your problem whenever you need one: PDF and email text, with the final reminder and your next step. Cancel any time.
Facts from this page's own sources · a small team in Amsterdam · no ad networks · delete everything any time
📜 The rules in France
Grid connection
Ask Enedis for a new connection online via Connect-Racco. Enedis estimates 2–6 weeks for the quote, 6–18 weeks for the work and 1–2 weeks for switching on, depending on distance to the grid and power. Costs follow Enedis's published connection price schedule.
- Before switching on you need a supply contract, the paid connection invoice and a Consuel certificate for your indoor wiring. (enedis.fr)
- If a connection takes too long, you can go to the Médiateur national de l'énergie after a written complaint. Disputes about access to the grid can also go to CRE's dispute committee (CoRDiS), which does not award compensation. (service-public.gouv.fr)
🪜 Step by step
- Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
- Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for France below.
- Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
- Complain if it goes wrongComplain to the grid operator first, then to the body named below.
📇 Who to contact
❓ Questions
Who pays for the connection?
Usually the customer pays a connection charge set by the grid operator or the regulator.
Why does my grid operator refuse or delay?
Sometimes the local grid is full. Ask for the reason and the expected date in writing.
Do I need a new connection for solar panels?
Often not for small systems, but you usually have to register them with the grid operator.
📎 Sources
- enedis.fr › quel est le delai pour un raccordement electrique →
- enedis.fr › raccordement maison →
- service-public.gouv.fr →
- cre.fr › demande de reglement des differends →
- connect-racco.enedis.fr →
- enedis.fr →
- cre.fr →
- energie-mediateur.fr →
🧭 Is this still correct?
We check this information carefully, but phone numbers, websites and rules change — and sometimes we get something wrong. Spotted a mistake or a change? Let us know below.
This form only corrects this page. It does not go to the police or any authority, and nobody will act on what you write. To report something, use the contacts on this page. In an emergency, call the emergency number. Do not write names, number plates or other people's details here.
⚠️ Readers report that something here may have changed — we are checking it.
✅ Thank you — this keeps the page up to date for everyone.