New or bigger grid connection in Malta: how long may it take and who do I complain to?
A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.
FFCheck One: every FFCheck Letter included, €4.99 a month
A formal letter for your problem whenever you need one: PDF and email text, with the final reminder and your next step. Cancel any time.
Facts from this page's own sources · a small team in Amsterdam · no ad networks · delete everything any time
📜 The rules in Malta
Grid connection
Enemalta must connect any premises on application and payment of the fee (S.L. 545.41, regulation 3): €300 for a single-phase connection, €600 for 40 A three-phase, €900 for 60 A three-phase, signed off by an authorised electrician. A standard connection up to 60 A is made by extending the network from the nearest suitable point; beyond 150 metres you pay the full cost of the extension less the fee (regulation 8). The law sets no time limit; REWS reports that in 2024 Enemalta took on average 12.9 days from application to installing the meter for a new non-complex connection.
- Visits: Enemalta must give at least four working days' written notice before entering your premises (two for a disconnection), its staff must show an ID card and you may refuse entry to anyone without one. You can reschedule a connection appointment free of charge within 15 working days on a weekday between 8am and 4pm (regulation 18, Sixth Schedule). (legislation.mt)
- Complaints about connection or voltage quality go first to Enemalta plc. Complaints against the network operator can then be referred to REWS, which must decide within four months (extendable by two months with your agreement). (rews.org.mt)
- Applications for a new electricity service are submitted to ARMS Ltd using its application forms. (arms.com.mt)
🪜 Step by step
- Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
- Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for Malta below.
- Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
- Complain if it goes wrongComplain to the grid operator first, then to the body named below.
📇 Who to contact
❓ Questions
Who pays for the connection?
Usually the customer pays a connection charge set by the grid operator or the regulator.
Why does my grid operator refuse or delay?
Sometimes the local grid is full. Ask for the reason and the expected date in writing.
Do I need a new connection for solar panels?
Often not for small systems, but you usually have to register them with the grid operator.
📎 Sources
- legislation.mt →
- rews.org.mt › 2025 Malta National Report Final (PDF) →
- arms.com.mt →
- enemalta.com.mt →
- enemalta.com.mt › contact →
- rews.org.mt →
- rews.org.mt › dispute resolution →
🧭 Is this still correct?
We check this information carefully, but phone numbers, websites and rules change — and sometimes we get something wrong. Spotted a mistake or a change? Let us know below.
This form only corrects this page. It does not go to the police or any authority, and nobody will act on what you write. To report something, use the contacts on this page. In an emergency, call the emergency number. Do not write names, number plates or other people's details here.
⚠️ Readers report that something here may have changed — we are checking it.
✅ Thank you — this keeps the page up to date for everyone.