← FFCheckElectricity & gasHR
Electricity & gas · Croatia
Checked 2026-09-30

🔗 New or bigger grid connection in Croatia: how long may it take and who do I complain to?

The short answer

A new home, a heat pump, a charging point or solar panels can need a new or bigger connection. The grid operator does this work, and many countries set deadlines and rules on costs.

📜 The rules in Croatia

Grid connection

For a simple household connection, HEP ODS must issue the electricity approval (EES) within 15 days of a complete request and send a connection offer, valid for two years. It must build the connection within 30 days of full payment of the connection fee.

  • The 30-day build deadline applies only if your installation meets the conditions for a network-use contract. These rules were adopted by HEP ODS in 2023 with HERA's prior consent. (hep.hr)
HEP - Operator distribucijskog sustava d.o.o. (HEP ODS)Handles connection requests, issues the EES and builds the connection.🔗 hep.hr
Official source: hep.hr · Checked 2026-09-30

🪜 Step by step

  1. Apply to the grid operatorApply to the grid operator for your address, not your supplier. Say what you want to connect and the capacity you need.
  2. Ask for a quote and a dateThe grid operator should tell you the cost and when the work will be done. See the rules for Croatia below.
  3. Keep track of deadlinesWrite down the dates. If a deadline is missed, ask why in writing.
  4. Complain if it goes wrongComplain to the grid operator first, then to the body named below.

📇 Who to contact

HEP - Operator distribucijskog sustava d.o.o. (HEP ODS)Handles connection requests, issues the EES and builds the connection.🔗 www.hep.hr/ods
HEP - Operator distribucijskog sustava d.o.o. (HEP ODS) — Croatia, 21 distribution areas (elektre)Runs the local grid, meters and connectionsPower cut, meter problem, new connection🔗 www.hep.hr/ods
Hrvatska energetska regulatorna agencija (HERA)Supervises energy companies and explains your rightsFor information, and to report a company that breaks the rules📞 +385 1 6323-777🔗 www.hera.hr

❓ Questions

Who pays for the connection?

Usually the customer pays a connection charge set by the grid operator or the regulator.

Why does my grid operator refuse or delay?

Sometimes the local grid is full. Ask for the reason and the expected date in writing.

Do I need a new connection for solar panels?

Often not for small systems, but you usually have to register them with the grid operator.

📎 Sources

Checked: 2026-09-30

🧭 Is this still correct?

We check this information carefully, but phone numbers, websites and rules change — and sometimes we get something wrong. Spotted a mistake or a change? Let us know below.

🔗 Also useful

More help in Croatia